Annual Compliance Summary — 2026
SN Month Total Readings Alert Events (Below Threshold) Avg Flow (m³/h) Compliance Rate Action
1 January 2026 0 0 0
2 February 2026 0 0 0
3 March 2026 0 0 0
4 April 2026 0 0 0
5 May 2026 0 0 0
6 June 2026 64 0 3309.16
100.0%
View
7 July 2026 0 0 0
8 August 2026 0 0 0
9 September 2026 0 0 0
10 October 2026 0 0 0
11 November 2026 0 0 0
12 December 2026 0 0 0
Regulatory Compliance — Government of Himachal Pradesh

The Sainj Hydro Electric Project (100 MW), located at Sainj, Kullu District, Himachal Pradesh, is mandated under HP Government notification to maintain an Environmental Flow (E-Flow) of 3,000 m³/h (representing 15% of the total average annual flow) at all times to ensure the ecological sustainability of the Sainj River. This annual report provides a month-wise overview of compliance for the year 2026.